Horn of the Moon culvert replacement was completed on 10/3/25 and road reopened! (It was closed on Tuesday, 10/7/25, for guardrail installation.)

Thanks to Gideon from Mangan Excavation LLC for nice work and quick turnaround!!

Horn of the Moon Culvert Replacement Construction is Complete – The culvert is reopened on 10/3/25!! The project started, July 22, 2025, and digging began on Wednesday, July 23, 2025. Vendor set the box culvert on September 10, 2025. The road was put in 10/2/25. The culvert will be closed Tues, 10/7/25 for guard rails installation.

Here are pics from 10/5/25 before the guardrails.


Here are pics from 9/23/25 mid project.