East Montpelier was awarded CDBG and MPG Grants for revitalizing, building Master Plans, and bringing more housing to the Village of North Montpelier and this is the project page for both of these projects. Please see the document library below for both Downtown North Montpelier and Orchard Valley Waldorf School Master Plan Projects. For these projects, the vendor selected by the town was SE Group, the town is the client, the Selectboard is the decision-maker and Town Administrator at manager@eastmontpeliervt.org is the point of contact. And a big thank you goes out to all the stakeholders, project team members, residents & volunteers, such as Celina Barton, Chair of the Grants Committee, who have donated endless volunteer hours from project inception to current date! Also a big thank you to Lisa Kreis, resident of North Montpelier, for the beautiful handmade crafted musical quilt that is currently in the town office for auction for fundraising for the match to help fund the project! Please email any bids to manager@eastmontpeliervt.org opening bid is $300! Click here for the Quilt Auction Information (click here)
Please email any project questions to manager@eastmontpeliervt.org and/or please email manager@eastmontpeliervt.org if you would like to be added the stakeholder list.
High Level 2026-2027 Project Schedules:
Month Downtown Village Plan Orchard Valley Waldorf School Plan
July Existing conditions Existing conditions
Aug Site analysis report Site analysis report, site walk
Sep Site visit + open house
Oct Framework alternatives Framework alternatives
Nov Public presentation Public presentation
Dec Document finalization Document production
Jan Document finalization
Feb Final Plan
260923_NoMo and OV Updated Engagement Timeline
Meetings:
1. KICK OFF MEETINGS-
-North Montpelier Downtown Master Plan – Project kick off meeting, Tues, July 7, 2026, 3pm-4pm- Introductions, Roles & Communication, Project Vision & Basemaps, Project Schedule & Synergy Review
-Orchard Valley Waldorf School Master Plan – Project kick off meeting, Tues, July 7, 2026, 4pm-5pm- Introductions, Roles & Communication, Project Vision & Basemaps, Project Schedule & Synergy Review
2. SITE VISITS-
-8/7/26 Orchard Valley Waldorf School Master Plan – 2 hour Site Visit, meet at OVWS at 10:30am and walk and hike site and trails. SE Group team’s landscape architects Hannah Loope and Elena Juodisius will meet the Project Team there on site with basemaps and look forward to learning from your experience and knowledge to lead a full tour of the developed and undeveloped sides of the property. SE Group to compile the information from site visit and our other research into a “Clarification of Assumptions and Constraints Memo”.
-8/14/26 North Montpelier Downtown Master Plan – 2 hour Site Visit 8/14/26- meet at town office at 9am, drive together in town truck to North Montpelier, park and walk, & hike the village & trails. The priority will be absorbing this group’s awareness and institutional knowledge, and doing some thorough photography to document site conditions throughout the village. Dayton from SE Group will document site conditions, meet key landowners or stakeholders, and learn more about what has been and could be in store for the future with this Village Core. (Orchard Valley representation is welcome at this site tour, but not required)
3. SEPT OPEN HOUSE MEETING– Sept 25, 2026 NoMo Open House Flyer
• When: Friday, September 25th, 4-6 PM
• Where: 2850 Route 14 North, North Montpelier VT
• What: Provide your input on the projects and meet the planning team
• SE Group Plans to Use AI Transcriber @ Open House: Internally, SE Group is planning on using Plaude – a recording device that will use AI to transcribe voice, as part of a ‘tell your North Montpelier Story’ board which is totally optional only for those who would like to. SE Group will have their human team go through and select salient elements of the transcription for use in the plan, but feel it’s a great way to let people ‘just talk’ and have their feedback recorded. (totally optional and If there is any discomfort with this approach, they would be happy to adjust and pull back on this use of a ‘techy’ tool – just let the vendor know.)
• Can’t Make it to the Open House? Take the Community Survey! The survey takes approximately 10-15 minutes to complete. Your response will be anonymous. It will be used to help inform recommendations for the NoMo Village Revitalization Plan. North Montpelier Master Plan Open House Survey (click here)
4. MONTHLY VENDOR PROJECT MANAGEMENT TEAM MEETINGS ONGOING via teams- “East Montpelier Projects: OVS 1st Half, NoMo 2nd Half Stakeholder Meetings” are held: Occurs the fourth Wednesday of every 1 month(s) effective 8/26/2026 until 8/26/2027 from 2:00 PM to 3:30 PM via teams meeting. Request to be added to: manager@eastmontpeliervt.org
-9/23 Scheduled Meeting Agenda & Attendance – The focus of this meeting will be coordinating last minute details about the open house, finalizing surveys and community engagement board.
The Vendor’s Regular Monthly Meetings coming up are=
-Nov 18, provide feedback on the Preliminary Plans to SE Group, for MPG they want feedback before 11/24/26
-Dec 23
-Jan 27
5. Nov 12, 2026, OVWS & SE Group is having an additional meeting to vet preliminary plans 1-2pm via teams.
6. OVWS Community Engagement Meeting in Jan 2027.
Preliminary Master Plans/Development Scenarios for Review:
261110_North Montpelier Village Plan_DRAFT
Please provide your feedback and/or questions for SE Group to manager@eastmontpeliervt.org, by 11/23/26.
Document Library:
SE Group Project Management OneDrive Link for both projects
Site Photos
SE Group Meeting Schedule
SE Group 7/7/2026 Kick off Call Deck
SE Group Memo 8.21.2026 NoMo and Orchard Hill Community Engagement Survey_dc
Sept 4, 2026 Orchard Valley Site Inventory and Analysis by SE Group
Sept 23, 2026 Orchard Valley Site Inventory and Analysis – Comments by Celina Barton
July 23, 2026 OVWS School Use and Potential House site/initial landscape map
Orchard Valley Waldorf School Topographical Map
2019 -Proposed North Montpelier Village Center Map
Orchard Valley Waldorf School Baseline Materials Transmittal Memo
MPG and CDBG Project Stakeholder Lists 6.3.26
Survey:
North Montpelier Master Plan Open House Survey Link (click here)
North Montpelier Master Plan Survey Results as of 10.1.26
Orchard Valley Waldorf School Draft Survey Link (click here)- Draft Only
OVWS Documents:
1. Warranty Deed : recorded in Book 87 Page 257 (pdf 3274) click here
2. Quit Claim Deed: recorded in Book 89 Page 279 (pdf 3639) click here
3. Land Use Permit 5W1456 recorded in Book 94 Page 249 (pdf 4559) click here
4. Land Use Permit 5W1456B Administrative Amendment recorded in Book 111 Page 163 (pdf 7737) click here
5. Warranty Deed Orchard Valley School Bk 113 Page 441(pdf 8157) click here
6. Land Use Permit 5W1456-1 recorded in Bk 177 Page 115 (pdf 15127) click here
Grant Information:
For Grant Information (click here)
Prior Work Incorporated:
1. Capstone Project-College Theses Project by Tommy Barton (click here)
2. Previous OVWS Plan/Site documents from Orchard Valley Waldorf School (click here)
Existing Conditions Document from SE Group:
North Montpelier Existing Conditions- draft #1 (final to come shortly)
Progress Reports:
July Progress Reports from SE Group:
July 13, 2026 North Montpelier Downtown Progress Report
July 13, 2026 Orchard Valley Waldorf School Progress Report
Aug Progress Reports from SE Group:
Aug 6, 2026 North Montpelier Downtown Progress Report
Aug 6, 2026 Orchard Valley Waldorf School Progress Report
Sept Progress Reports from SE Group:
Sept 3, 2026 North Montpelier Downtown Progress Report
Sept 3, 2026 Orchard Valley Waldorf School Progress Report
SE Group Invoice.10.5.26. 8197-Town of East Montpelier CDBG-DR Planning Grant_ Orchard Valley
Sept SE Group Open House Concept Boards/ Public Engagement Boards:
SE Group Public Engagement Boards for Community Feedback for the open house
Oct Progress Reports from SE Group:
Oct 9, 2026 Progress Report_MPG Grant_North Montpelier Village Master Plan
Oct 9, 2026 Progress Report_CDBG-DR Grant_Orchard Valley Housing Feasibility
Nov Progress Reports from SE Group:
261110_Progress Report_MPG Grant_North Montpelier Village Master Plan
261104_Progress Report_CDBG-DR Grant_Orchard Valley Housing Feasibility
Maps
Development Map
Site Analysis Maps

Forest Blocks Map

Septic Suitable Map

Slopes Map

Solar Map

Utilities Map

SE Group Project Team:
SE Group- Dayton Crites, a lead planner & designer with SE Group, who will be supporting our team’s work on both Orchard Valley and North Montpelier plans
SE Group- Hannah Loope, Project Manager
Notes:
- 7/8/26 SE Group requested the Town Plan completion date: The Planning Commission is aiming for completion of the Town Plan in 2027, and also the PC does not have a more precise timeline yet.
- Per Tommy, …Looking forward to future grants, we would love to be set up to win the Catalyst grant for next year when we have the MPG complete. It supports projects in a wide range of activities including:
– Modernize and expand access to public water and wastewater services,
– Revitalize transportation infrastructure,
– Establish workforce development programs and facilities,
– Grow the outdoor recreation economy, and
– Provide access to new childcare and healthcare facilities.
Projects that are given priority will demonstrate readiness, be consistent with the economic development goals of the region and will advance a combination of NBRC and member state priorities.
If we could determine how to best position ourselves to secure this next year that would be a wonderful result from the MPG.
3. CHIP is also a program that could be considered for the next phase, on the the implementation road map.
4. Please email any feedback or inputs about the draft plans or questions to manager@eastmontpeliervt.org.